The following timeschedule was presented:
By the end of october 2014 all building should be finished
By the end of november all interactives should be finished
First two weeks of december 2014 system and users tests.
Grand opening of the RP Hub on the 14 th of decmber 2014.
RP HUB build phase leaders
Bim Rasmuson and Rathmeous Dagger - Fantasy
Xentor Antarix and Lunastra Silverweb - SciFi
Fire Nice and Sophia larkspur - Literary fantasy
Chopper Gurbux and Misty Harley - Urban
Lanorra Sion and Beck Howard- Dark fantasy
Cassie Eldemar - Library build
Oldesoul Eldemar - Grand opening event
Balpien Hammerer, Boudica Destiny, Boaz Sands and Astoria Luminos - interactive elements library
Wolf Hartnell - Overall script management
Astoria Luminos and Boaz Sands - Estate Managers/ overall assistance/ guardians of initial guidelines
Moontan Valeeva - leader of the overall project